1. You are entering tasks in a project you are tracking in Microsoft
Office Project Standard 2007. You enter the duration of each task. Then
you assign multiple resources to each task. As a result, the duration
of the tasks changes.
You want the duration of all future tasks to automatically remain the same when you assign resources to those tasks.
What should you do?
A. Enable the manual calculation mode.
B. Change the duration of all existing tasks.
C. Change all existing tasks to be of fixed duration.
D. Change the default task type to fixed duration.
Answer: D
2.You are creating a project management methodology. You document
project management procedures and create specialized project management
process templates.
You need to apply the processes in the context of Microsoft Office Project Standard 2007.
What should you do first?
A. Create a Project Guide.
B. Display the Task Drivers pane.
C. Display the Hyperlinks column.
D. Display the Microsoft Office Online Web site.
Answer: A
3. You are entering tasks in a project plan in Microsoft Office Project Standard 2007. Each task has an estimated duration.
You need to make sure that no task in this project plan has a question mark in its Duration field.
What should you do?
A. Disable the option to show that tasks have estimated durations.
B. Change the width of the Duration column so the question mark is not visible.
C. Create a new project plan based on a template that does not have estimated durations.
D. Re-enter the same durations so the question marks representing the estimates disappear.
Answer: A
4. You measure the performance of a project you are tracking in
Microsoft Office Project Standard 2007 by updating the completion
percentage of the tasks. The actual cost of work performed (ACWP) for
all tasks is $0.00. The project has a baseline and all values have been
calculated.
You need to ensure that the ACWP shows data other than $0.00.
What should you do first?
A. Assign budget resources to the project summary task.
B. Enter standard resource rates that are greater than zero.
C. Select the Manual calculation mode, and then perform a calculation.
D. Select the Physical % Complete option for earned value purposes.
Answer: B
5. You are tracking a project in Microsoft Office Project Standard
2007. Assigned resources report status based on the actual work and the
actual duration.
You need to configure Project so that you can independently record the actual work and the actual duration.
What should you do first?
A. Activate the Updating task status updates resource status option.
B. Deactivate the Updating task status updates resource status option.
C. Activate the Edits to total task % complete will be spread to the status date option.
D. Deactivate the Edits to total task % complete will be spread to the status date option.
Answer: B
6. You create tasks in a project plan in Microsoft Office Project Standard 2007.
You need to see the project start and finish dates and the task start
and finish dates on the table side of the Gantt Chart view.
What should you do?
A. Display the Work table.
B. Display the Schedule table.
C. Display the project summary task.
D. Generate the default project summary overview report.
Answer: C
7. In Microsoft Office Project Standard 2007, you are creating a
project plan from a list of serial tasks you have captured on paper.
You have entered ten tasks in order and entered predecessors for all
but the first task.
You then notice that the eighth task should actually be between the fifth task and the sixth task.
You need to put the tasks in the correct order.
What should you do first?
A. Set the eighth task type to Fixed Duration.
B. Enter 8 in the Successor field of the sixth task.
C. Enter 6 in the Predecessor field of the eighth task.
D. Activate the Autolink inserted or moved tasks option.
Answer: D
8. In Microsoft Office Project Standard 2007, you create three tasks in
a project plan by using the manual calculation mode. After you create
the tasks, the Gantt chart displays the following image:
You need the Gantt chart to automatically display the tasks in sequence instead of in parallel.
What should you do?
A. Display the Calendar view.
B. Perform a project calculation.
C. Set the project options so that Project automatically links inserted or moved tasks.
D. Set the project options so that Project automatically adds new resources and tasks.
Answer: B