IBM IBM certifications I 000-078 Web Demo
This webdemo is just a demo data, only for reference and learning, there is no other purposes
1.After installing a new BladeCenter, IBM Director has successfully
discovered the new chassis. Which of the following tasks must first be
performed before launching the Deployment Wizard in IBM Director?
A. Update the BladeCenter Management Module firmware
B. Enable the Ethernet switch ports for external management
C. Select "Request Access" to the Management Module
D. Move the Management Module Ethernet port to a management VLAN
Answer: C
3. What is an important benefit of using a switch compliant to IEEE 802.1Q?
A. The switch allows multiple proprietary protocols to forward traffic between switches.
B. The switch allows use of logical groups within a switch in order to control broadcast traffic.
C. The switch can combine physical links into one point-to-point logical link for increased bandwidth.
D. The switch discovers a loop-free network (tree) and provides a single physical path between any two stations.
Answer: B
4. A customer wants to set up a 512 node (HPC Cluster) BladeCenter
environment for an extremely high bandwidth application. Which of the
following is the most appropriate switch module to interconnect the
multiple chassis needed?
A. Topspin Infiniband Switch Module
B. BladeCenter Copper Pass-thru Module
C. BladeCenter Optical Pass-thru Module
D. Nortel Networks Layer 2-7 GbE Switch Module
Answer: A
5. Which of the following can be used to update firmware on all Ethernet switch module options?
A. FTP
B. TFTP
C. Web Browser
D. Management Module
Answer: B
6. An administrator has created a customized Linux Native Install
operating system image to deploy to the blades. When the administrator
creates a task that uses this image, the installation fails. Which of
the following is the most likely cause?
A. boot.ini is incorrectly configured
B. All packages and package groups had been selected
C. Only the required packages and package groups were installed
D. The packages and package groups present in the modified comps file were not selected
Answer: D
7. A customer wants a new BladeCenter chassis installed with redundant
power sources. What is the minimum PDU configuration, recommended by
IBM, to support a single chassis fully populated with 2000W power
supplies?
A. 2 Rack PDUs - 100-127Vac, 15a
B. 1 Front End PDU - 208Vac, 30a, single-phase
C. 2 Front End PDUs - 208Vac, 30a, single-phase
D. 2 Enterprise PDUs - 208Vac, 60a, single-phase
Answer: C
8. What is the default network address of the Management Module and any modules placed in an I/O module bay?
A. 192.0.0.x
B. 192.16.70.x
C. 192.168.0.x
D. 192.168.70.x
Answer: D
2. Which TWO of the following hardware alerts can be sent to each blade server's IBM Director agent?
A. Fan Alert
B. Virus Alert
C. Voltage alert
D. Intruder Alert
E. Temperature alert
F. Power Supply failure
Answer: CE